Installation should include assembly according to the approved instructions, inspection of cables and connectors, verification of protective grounding, functional checks for controls and moving parts, and a documented commissioning test. The installer should confirm that the red light therapy bed is stable, that panels and covers are secure, and that fans or cooling channels are not blocked.
The final handover should identify the installed model, serial number, software or firmware version where applicable, date of commissioning, installer name, measured electrical checks, and any open issue. The customer should receive a signed copy instead of relying on a verbal statement that the unit is ready.